"When do we get the keys?" It's usually the second question after price, and for good reason. Your rent, your children's school plans and your loan EMIs all hang on it. For Godrej Florenne, the Godrej row-villa community off Soukya Road that launched in September 2026, there's now a RERA registration to anchor the answer. But the dates reported by different sources don't all match, so let's take them one at a time.
What has been reported so far
Godrej Florenne is registered with Karnataka RERA in two phases. The Phase 1 number is PRM/KA/RERA/1250/304/PR/150926/008942, listed on the main project site and on PropertyPistol. PropNewz also gives a Phase 2 number, PR/150926/008943, and a registration date of 15 September 2026, which fits the "150926" date code inside both numbers.
On possession, the sources differ. PropNewz's review reports RERA completion dates of 8 October 2030 for Phase 1 and 8 October 2031 for Phase 2. PropNewz's project page and PropertyPistol say September 2030. The main project site says September 2031. And an older pre-RERA listing on Housiey said December 2029. Our reading is that the phase split explains most of this: 2030 is the Phase 1 date and 2031 the Phase 2 date. We could not open the Karnataka RERA portal record ourselves, so treat all of these as reported. Summary: around October 2030 for Phase 1 and October 2031 for Phase 2, as reported.
| Source | Possession figure given |
|---|---|
| PropNewz review (RERA dates) | 8 Oct 2030 (Phase 1), 8 Oct 2031 (Phase 2) |
| PropNewz project page, PropertyPistol | September 2030 |
| Main project site | September 2031 |
| Housiey (pre-RERA listing) | December 2029 |
How the official date gets fixed
Under the Real Estate (Regulation and Development) Act, every project has to declare a proposed completion date when it registers with the state authority. In Karnataka, that's the Karnataka RERA portal. You can search the registration number there and see the declared completion date for each phase on the public record.
That date then flows into your agreement for sale. The agreement must state when the developer will hand over possession. If the developer misses it, the Act gives buyers the right to claim interest for every month of delay, or to withdraw and get a refund with interest. So the RERA date is the one with legal weight. Our RERA guide for the project explains how to read the registration. Summary: the binding date is the one on the RERA record for your phase and in your agreement.

Working out a realistic timeline
Let's do the arithmetic for Godrej Florenne the way we would for a client. From a September 2026 registration to October 2030 is about four years and one month for Phase 1. Phase 2 gets one more year, about five years and one month. Row villa communities in Bengaluru typically take three to four years per phase to build, depending on the number of homes and approvals. That's a general pattern for this kind of product, not a Godrej-specific figure.
So the reported Godrej Florenne dates look comfortable rather than tight. Developers usually declare a RERA date with some buffer built in, because missing it has a cost. Reported unit counts vary between sources, from 218 to 240 or more villas, on about 20 acres. Splitting that into two phases means each phase is a manageable build. Low-rise homes also let work run on many villas in parallel. Summary: about four years for Phase 1 and five for Phase 2, which fits a typical villa build with buffer.
The video below gives a look at the Godrej row villas on Soukya Road from around launch time, which is useful if you want a feel for the product while you plan around the possession schedule.
What the developer's record tells you
Godrej Properties is a listed company. In FY25 it reported sales bookings of ₹29,444 Cr and about 18.4 million sq.ft of deliveries. A developer handing over that much space in a single year has well-practised systems for construction and delivery. That doesn't replace checking the RERA date for your phase, but it does tell you the company has the scale to execute a 20-acre community. Our builder track record page looks at this in more depth.
Being listed adds another layer. The company reports its launches, deliveries and financials to the stock exchanges every quarter, so there's a regular public trail you can follow while your Godrej Florenne villa is being built. Summary: strong delivery numbers and public reporting give you good visibility, but the RERA date is still your anchor.
Planning your own finances around the date
We'd suggest you plan step by step. First, assume the later reported date for your phase. If you're renting and you book in Phase 1, plan to pay rent until late 2030 and treat anything earlier as a bonus. In Phase 2, plan for late 2031. Second, look at your payment plan. In a construction-linked plan, most of the money is paid as the building progresses, so your loan disburses gradually rather than all at once. Our payment plan guide explains the usual stages.
Third, think about pre-EMI interest on your Godrej Florenne villa. If your loan disburses in stages, you pay interest only on the amount released until full disbursement. On a ₹4.32 Cr loan for the Optima (80% of the listed ₹5.40 Cr base), the pre-EMI interest will climb steadily over four years. A Phase 2 villa means one more year of it, which is a real cost to factor in. Fourth, keep a buffer for interiors and moving. Villas take longer to furnish than apartments, and many families spend three to six months on interiors after handover. Summary: budget for the later date, account for pre-EMI interest and leave time for interiors.

Questions to ask at booking
When you book at Godrej Florenne, ask which phase your villa falls in and what completion date is declared for that phase on RERA. Ask whether the possession clause in the agreement matches the RERA date exactly, or whether there's a grace period. Ask how the developer will update buyers on progress, whether through site visits, photos or a customer portal. And ask whether the clubhouse and common amenities will be ready at the same time as the homes in Phase 1.
Read our explainer on possession timelines and delay clauses before you sign, so you know what the standard terms mean. As construction moves, our construction status page will track progress as it's reported.
Where things stand today
To put it all together: Godrej Florenne launched in September 2026 off Soukya Road, on the eastern edge of Whitefield, with two RERA-registered phases. The reported completion dates are 8 October 2030 for Phase 1 and 8 October 2031 for Phase 2. Other sources round these to September 2030 or September 2031. Check the RERA record and your agreement for the date that applies to your villa. Construction progress on a villa project is also easy to see for yourself, because the homes are low-rise and the site is open, so a visit every few months tells you a lot.
Final summary: plan around late 2030 for Phase 1 and late 2031 for Phase 2, confirm your phase's date on RERA at booking, and make sure the same date appears in your agreement.
Sources: Karnataka RERA, PropNewz project page and review (reported RERA numbers and dates), PropertyPistol listing, godrejflorenne.net.in, Housiey listing.
Godrej Florenne Possession Date FAQs
When is possession expected at Godrej Florenne?
PropNewz reports RERA completion dates of 8 October 2030 for Phase 1 and 8 October 2031 for Phase 2. Other sources give September 2030 or September 2031. Treat these as reported until you see the date on the Karnataka RERA portal and in your agreement for sale.
Will all villas be handed over at the same time?
No. The project is registered in two RERA phases, and each phase has its own completion date. Ask which phase your villa falls in at booking, and check that phase's registration number and date on the RERA portal before you pay.
What happens if possession is delayed?
Under the RERA Act, the possession date in your agreement for sale is binding. If it is missed, buyers can claim interest for each month of delay or choose to withdraw and seek a refund with interest. Read the possession clause carefully before signing.
How should I plan my rent and loan around possession?
Budget for the later reported date of your phase, so plan rent until late 2030 for Phase 1 or late 2031 for Phase 2. Factor in pre-EMI interest on a staged loan, and leave three to six months after handover for interiors.